Written decisions in the mandamus and agency-delay group decided in 2011, and agency-delay suits filed in 2011.

2,914 written decisions from 2,661 cases in the whole mandamus and agency-delay group, the group's newest decided October 30, 2026. Updated November 3, 2026 at 1:24 a.m. CT; the Passim connector counts the live collection, which can differ by the day's additions and retirements (which total to quote). Coverage: of the 1,606 public decisions since January 1, 2025 that a CourtListener and GovInfo search for mandamus and agency delay finds, Passim holds 1,371 (85%), measured November 3, 2026. Some of what that search finds are not mandamus decisions. Tell us about a decision we're missing.

These are counts of past written decisions and dockets, not predictions of how any case will be decided. A distribution appears only when at least 5 decisions (or 5 dockets) are behind it; smaller groups are listed, not summarized. How it's counted.

How the decisions came out

This page counts 17 of the group's written decisions, from 17 cases; the newest of them was decided December 9, 2011. The line at the top counts the whole group.

17written decisions
17cases they come from
1decisions weigh the TRAC factors
51.7median months from the application to the suit

Each case counts once in these outcome counts, by its latest decision here. A motion to dismiss denied and a later judgment for the government count as the judgment. How decisions are grouped into cases.

Disposition, by case

  • Granted (either side's motion)1
  • Denied (either side's motion)3
  • Dismissed8
  • Dismissed in part; some claims go on2
  • Remanded to the agency3

Prevailing party, by case

  • Applicant4
  • Government10
  • Each side in part3

Months from the application to the suit

51.7 months at the median; half fall between 23.6 and 82.8. 7 cases state it.

1 of these is a section 1447(b) naturalization suit, whose months run from the application; the statute's 120 days run from the interview, which these figures do not measure.

Months from the application to the court's decision

19.3 months at the median; half fall between 9.2 and 44.2. 11 decisions state it.

Leaves out the 2 decisions holding that the agency had acted: their months to the decision are not a delay.

What the suits asked for, by case

  • Decide the application3
  • Schedule an interview1
  • Naturalization hearing or remand (1447(b))1
  • Some other action3
  • Not recorded9

Agency, by case

  • USCIS12
  • Department of State2
  • CBP1
  • DHS1
  • Department of Justice1

Form or filing, by case

  • I-485 (adjustment of status)6
  • DS-260 (immigrant visa)1
  • I-129 (worker petition)1
  • I-140 (immigrant worker petition)1
  • I-360 (special immigrant petition)1
  • I-539 (change or extension of stay)1
  • I-589 (asylum)1
  • I-765 (EAD)1
  • N-400 (naturalization)1

Courts with the most decisions

Download these 17 decisions as a spreadsheet (CSV).

Examples

The newest case with each of the most common dispositions, by its latest decision.

How agency-delay suits ended

Most suits end without a written decision: the agency acts and the parties dismiss. These counts come from the docket record (the federal courts' Integrated Database and CourtListener) and count every mandamus, APA and section 1447(b) suit against any immigration agency filed in 2011. Check a delay counts fewer: a court's suits of the last three years against the form's agency.

2 dockets: fewer than 5, so no distribution is shown. List them.